• Facebook
  • Instagram
  • Youtube
  • TikTok
  • Contact Us
Community Land & Water Coalition, Inc.
  • Home
  • About Us
    • Grassroots Organizing & Advocacy
    • Indigenous Rights and Culture
    • CLWC Leadership
    • Contact Us
  • Support Us
    • Ways to Support CLWC
    • Donate
  • Our Work
    • Stop Sand Mining
    • Protecting Wetlands, Waterways and Drinking Water
    • Forests & Biodiversity
    • Responsible Solar & Energy Siting
    • Take Action Right Now!
  • Resources
    • In the Press
    • Education
    • Blog
    • Podcasts
    • YouTube Channel
    • Newsletters
  • Events
    • Calendar
  • Search
  • Menu Menu

Tag Archive for: Plymouth Carver Sole Source Aquifer

Carver-Plympton: SLT Construction Mining Site: Archaeologically Significant

December 5, 2023

Archeological report states SLT’s Mining Site is “felt to have high potential for containing archeological resources” according to a preliminary study.

Excerpt:

 

This site was identified as having high potential for containing prehistoric archaeological resources. As well as being next to a pond, the soil is of the Carver Loam Series which are well drained soil, sandy soils, which were preferred.

Native populations favored ponds making Rickets pond likely a location of a prehistoric settlement. There are four recorded prehistoric sites located less than 2 kilometers from the project on spring street that were found during cultural management surveys. Two sites were found directly within the project area, indicating that there are likely additional sites could be present. 

Was a complete study ever done? Where is it? Today, the area is obliterated.

The preliminary archeological study done by the Mass Department of Transportation when it sold the land to SLT Construction is below.

SLT Spring St Carver 2018-04 PARP Archaeology Report from MASSDOT

Find out more about the SLT – Carver MA mining operation in the Sand Wars Report. 

https://communitylandandwater.org/wp-content/uploads/2026/03/FINAL-CLWC-LOGO-no-background-297x300.png 0 0 Meg Sheehan https://communitylandandwater.org/wp-content/uploads/2026/03/FINAL-CLWC-LOGO-no-background-297x300.png Meg Sheehan2023-12-05 22:21:232025-12-29 16:27:09Carver-Plympton: SLT Construction Mining Site: Archaeologically Significant

Plymouth & Carver: Plymouth Municipal Airport Operations Concern Residents

November 4, 2023

Airport Expansion Overview

The Plymouth Municipal Airport is in West Plymouth on South Meadow Road and extends into Carver.

The Airport Commissioners propose to extend the runway, build two new hangers, reconstruct a taxi lane and runway and extend water and sewer lines.   

UPDATE: January 16, 2024 State Issues MEPA “Certificate”

The Certificate is here MEPA Certificate Jan. 16, 2024

The Secretary of Energy and Environmental Affairs Rebecca Tepper says the Airport’s “Draft Environmental Impact Report” “adequately and properly” complies with the state’s environmental study law, MEPA. The next step is for the Airport to do a “Final Environmental Impact Report.”

The public’s comments submitted to the state made a difference!

The Airport has to do more study of the drinking water aquifer and how the Airport could impact water.

Attend Airport Commissioner’s Meetings.

Next meeting March 7, 2024 at 7 p.m. at the Airport

The agendas are posted here on the Town of Plymouth Website.

Contact the Airport Manager and Commissioners and ask to be on the Agenda to get your questions answered!

Plymouth Municipal Airport
246 South Meadow Road
Plymouth, MA 02360
Tel : (508) 746-2020
Fax: (508) 747-4483
Email: mcardillo@plymouth-ma.gov

Make comments and questions at public comment at the meetings.

Check out the Airport website

Demand transparency and accountability!

Demand compliance with the Open Meeting Law

Are their “executive sessions” legal?

Issues

Get the Fact Sheet by clicking here

  • Drinking water Will Airport expansion harm our drinking water? Section 4.2 of the study says drinking water wells are “not affected”. The study does not give enough information about this conclusion.
  • Our water comes from the underground Plymouth Carver Sole Source Aquifer. The groundwater is vulnerable to contamination.
    • The Town’s 2019 draft water system master plan says the Airport “is located adjacent to the Zone II area [protection area] for the Federal Furnace Well and could be a potential source for per and polyfluoroalkyl substances (PFAS).”
    • PFAS is a type of chemical that causes health problems, including cancer.
    • The Town’s 2019 draft water system master plan says we should be doing more to protect our wells: “Considering how susceptible the [Town’s] sources are to contamination; it is recommended that a more stringent groundwater protection district be developed.”
    • Private drinking water wells may also be impacted
  • Air pollution The study used an air station in Boston to conclude that air pollution is not a problem. The Airport must test current air pollution near the Airport and guarantee that the fumes from the Airport are not harming people now or in the future.
  • Noise and Light pollution

 

Find out more:

Airport Website Environmental Study

Get in touch: environmentwatchsoutheasternma@gmail.com

Below: MAP OF WELLS AROUND THE AIRPORT: Available at MassMapper GIS – a free mapping system from the Commonwealth of Massachusetts

 

https://communitylandandwater.org/wp-content/uploads/2026/03/FINAL-CLWC-LOGO-no-background-297x300.png 0 0 Meg Sheehan https://communitylandandwater.org/wp-content/uploads/2026/03/FINAL-CLWC-LOGO-no-background-297x300.png Meg Sheehan2023-11-04 20:31:502025-12-29 16:50:05Plymouth & Carver: Plymouth Municipal Airport Operations Concern Residents

Wareham: Two AD Makepeace Solar Proposals Denied Planning Board Special Permit Extension

November 18, 2022
Area of proposed solar development, 27 Charge Pond Road
Area of proposed solar development, 150 Tihonet Road
  • Citizens’ Groups extensively write to Planning Board to deny the permit extensions and urge Wareham to further study the safety and impacts of extensive solar installations within the Town.
  • Part of vast complex of sand mining and solar complexes throughout Wareham and Carver that have devastated biodiversity, wetlands and forests, AD Makepeace Co’s proposed solar installations at 27 Charge Pond Road and 150 Tihonet Road would have cut down an additional 111 acres of Pine Barrens forest.

June 10, 2024: The Wareham Planning Board denied site plan approval and special permit extensions for two solar proposals, one at 27 Charge Pond Road and the other at 150 Tihonet Road. Although the Board was not required to give a reason, they have previously expressed concerns with the safety of battery energy storage systems on site, the fact that the approvals are four years old already, and the fact that, if the approvals are extended, the Board will not have a chance to review the projects again, even though we are still possibly several years away from a project build-out.

Background – Planning Board and Citizens’ Actions:

January 8, 2024: The Wareham Planning Board contracted with safety expert Milosh Puchovsky to study the hazards associated with battery energy storage systems (BESS) and the applicable safety regulations. However, Mr. Puchovsky was unable to evaluate the safety and effectiveness of the applications for solar at 27 Charge Pond Road and 150 Tihonet Road as they were lacking in key information such as equipment specifications. The applicant said that equipment, and associated safety ratings, would not be identified until the projects were closer to implementation, but they would provide that information before breaking ground.

After hearing the results of Mr. Puchovsky’s initial response, and the fact that he was unable to perform a complete review of the projects due to lack of specifications, the Planning Board was unwilling to move forward on the extensions without the safety evaluation in place.

Monday, June 26, 2023: The Wareham Planning Board met on whether to deny the permit extension requests from Borrego Solar for the two destructive ground-mounted solar projects. A Citizens’ Group has submitted a letter to the Planning Board (below), stating all the reasons the permit extensions should be denied.

Citizens-Opposed-to-Extensions-of-27-150Download

Previously the Board requested more information on decommissioning, disposal costs for the solar panels, and the Town’s liability if Borrego/New Leaf walk away at the end of the lease. The Board asked the applicant to up the decommissioning cash bond to $2.2M. In December 2022, the Planning Board also raised serious concerns about the applicant’s irresponsible plans for decommissioning, as covered by the Wareham Week.

We are telling the Planning Board that the extensions should be denied and Borrego (now New Leaf) should reapply for the permits.

So much has changed since the site plans were approved in 2020.

  • Wareham residents voted to change to the Wareham solar siting bylaw to make it more protective of forests, natural resources, and wildlife habitat
  • There have been recent developments regarding state solar policy siting and criteria
  • A new increased awareness of the potential risks associated with Battery Energy Storage Systems (BESS)
  • New criteria adopted by the Wareham Fire Department in December 2022 regarding BESS 
  • Awareness of the cumulative impact of all of the deforestation/solar development in Wareham since 2020
  • New information about the costs of decommissioning
Community-Land-and-Water-Coalition-Public-Comment-27-Charge-and-150-TihonetDownload

The Planning Board approvals in 2020 were flawed in numerous ways. They did not adequately address impacts to Wareham’s water quality and wetlands. An expert report by Patrick C. Garner Co., Inc., dated May 8, 2021, identified two major defects in the wetlands applications for the solar arrays at 150 Tihonet Road and 27 Charge Pond Road. The precipitation data submitted to the Wareham Conservation Commission was climatologically obsolete. The applicant used 60-year old climatological data in the calculations of the stormwater retention requirements, rather than real-time precipitation data used by conscientious engineering firms. This means the stormwater systems approved by the Conservation Commission in 2020 are undersized by 20%. The report also documents that potential vernal pools are present on both sites, including four potential vernal pools at 27 Charge Pond Road and one potential vernal pool on 150 Tihonet Road. At least one of the vernal pools was biologically rich enough to certify; however the Wareham Planning Board approved the site plans without an Order of Conditions from the Conservation Commission, so they did not have this information.

Patrick-Garner-ReportDownload

Background – Improperly-Sited Solar’s Impact on the Natural Environment

We need both our forests and renewable energy in order to fight climate change.

  • A 2023 study by Mass Audubon and Harvard Forest concludes that we can meet our solar needs without clear-cutting our forests for projects like these.
  • A 2021 study shows that these 3 projects are a climate and biodiversity disaster – not a solution!
  • Solar belongs on rooftops and parking lots, not in our forests.

The area surrounding the proposed sites has already seen intense solar development.

Wareham has already lost over 300 acres of forest to solar development; it’s time for the Town put a stop to new solar projects that destroy forests in the name of clean energy. Science shows that preserving our forests along with their intact ecosystems and biodiversity are critical to addressing the climate crisis. Forests combat the effects of climate change by providing cooler temperatures, mitigating flooding, and purifying the air. Undeveloped forested land is crucial to sequestering carbon; in fact, according to the Massachusetts Decarbonization Roadmap, forests are the only proven technology that Massachusetts has for sequestering carbon. The pine barrens forests of Wareham must be preserved. Since 2000, it appears that the area has one of the highest rates of forest loss since 2000 in the entire state.

There has been no analysis of the impact on the Plymouth-Carver Sole Source Aquifer resulting from the deforestation from solar arrays in Wareham and Carver. The Plymouth-Carver Sole Source Aquifer is comprised of well-sorted, coarse grained silica sand, and water flows freely through it. There is very little relative attenuation time from when run-off or precipitation penetrates the ground surface to when it reaches the groundwater table. In fact, the water table is visible at the ground surface in Wareham’s ponds and rivers. Therefore, contaminants can be rapidly introduced into the aquifer system from a number of sources.

Watch You Tube videos of the impacts of solar development in Wareham here.

Growing Solar, Protecting Nature, a 2023 joint study by Mass Audubon and Harvard Forest, concludes that by protecting the most valuable natural and working lands from development, such as the forests at 27 Charge Pond Road and 150 Tihonet Road, Massachusetts could produce enough solar energy to meet our greenhouse gas emission reduction goals, while preserving 76% more forest carbon than our current trajectory would predict, and protecting nearly 100% of our remaining essential wildlife habitat and prime farmland.

Growing-Solar-Protecting-NatureDownload

Solar energy is a crucial component of our sustainable energy future. Unfortunately, the financial subsidies for solar have created unfortunate outcomes in land-use planning. Developers are taking the easy route and cutting down forests for solar instead of doing the hard work of planning solar on our built environment. Several groups, including the Wareham Land Trust issued a statement on solar siting in October 2021.

solar-siting-joint-statementDownload

Also, an EPA program called Re-Powering America’s Land aims to provide information and resources to solar developers and municipalities on the benefits of and considerations associated with siting solar development on contaminated land and landfills. The EPA is recognizing the need to conserve open space in the fight against climate change and providing resources to municipalities expedited the process associated with putting solar in previously developed land. It is possible to have solar power generation without cutting down forests, if planned and sited properly.

This is not about renewable energy – it is about saving our forests! State solar subsidies are providing financial incentives for large landowners to clearcut and lease their land, and we have to reverse course before it is too late!

For more information on what you have read, or for a myriad of additional reasons why these projects should not be approved, please contact Community Land and Water Coalition.

https://communitylandandwater.org/wp-content/uploads/2022/11/area-of-development.png 540 624 CLwpBS https://communitylandandwater.org/wp-content/uploads/2026/03/FINAL-CLWC-LOGO-no-background-297x300.png CLwpBS2022-11-18 16:19:212025-12-29 16:40:15Wareham: Two AD Makepeace Solar Proposals Denied Planning Board Special Permit Extension

Carver: Cranberry Point Battery Storage: MEPA state environmental review

September 30, 2022

MEPA RUBBER STAMPS Cranberry Point environmental report. See the Certificate here.

CLWC MEPA comments here and exhibits here

Carver Concerned Citizens MEPA comments here

Cranberry Point requires Massachusetts Environmental Policy Act (MEPA) review: read more here

MEPA is not a permit, but a study of alternatives that requires a developer to minimize and mitigate environmental damage from their project

Here is the state’s MEPA site for Cranberry Point

Read about the MEPA law here.

Community Land & Water Coalition and Carver Concerned Citizens October 13, 2022 press release on Cranberry Point:

Press-Release_-Groups-and-individuals-demand-that-the-Baker-Administration-reject-a-proposed-battery-facility-in-a-residential-neighborhood-in-CarverDownload

There are steps in the process:

An “Environmental Notification Form” (ENF)

Then a “Draft Environmental Impact Report” the public gets to comment on, and a “Supplemental Environmental Impact Report” (SEIR). The SEIR for Cranberry Point is here.

Finally, a “Final Environmental Impact Report” (FEIR) that is usually just a rubber stamp.

Weston-Carver-Battery-MEPA-150-MWDownload
August-13-2021-MEPA-ApplicationDownload

Oct-1-2021-MEPA-Certificate-16430-Cranberry-PointDownload
https://communitylandandwater.org/wp-content/uploads/2026/03/FINAL-CLWC-LOGO-no-background-297x300.png 0 0 CLwpBS https://communitylandandwater.org/wp-content/uploads/2026/03/FINAL-CLWC-LOGO-no-background-297x300.png CLwpBS2022-09-30 21:07:022025-12-30 16:30:53Carver: Cranberry Point Battery Storage: MEPA state environmental review

Archives by Month

Tags

AD Makepeace Aquifer Atlantic Coastal Pine Barrens Battery battery bomb Biodiversity Carver Carver MA corruption Craig Weston Cranberry cranberry bog Cranberry Country Corruption Cranberry County Corruption Deforestation DOER drinking water Earth removal Endangered Species Extinction Federal Road Forests Groundwater Indigenous Sovereignty Jim Kane Makepeace Massachusetts mining Pine Barrens Plymouth Reckless Development Resources sand and gravel Sand mining Solar Solar gone wrong Sole Source Aquifer strip mine Strip Mining Wareham Water water quality Wetlands Zoning Board of Appeals Zoning Violations

Community Land and Water Coalition

P.O. Box 1699, Plymouth, MA 02362
Email
Phone: 508-259-9154

Please consider making a donation to help strengthen our impact!

DONATE

You can sign our Sand Mining Petition to Governor Healy and town Selectboards here

Facebook
Facebook
fb-share-icon
YouTube
Instagram
Tiktok
JOIN OUR MAILING LIST

Join Our Email List

    Copyright © Community Land & Water Coalition   |   Privacy Policy   |   Site By LW Creative
    • Facebook
    • Instagram
    • Youtube
    • TikTok
    Scroll to top